Sunday 28 June 2015

Catching up

A little bit background about our build.

We put deposit on our place on 2nd May 2015. Back then, we didn't know much about anything except the location of the land. We didn't even have our mortgage pre-approved..... yea.....

We did a lot research and reading, ran around to different banks, tried to push everything going, so we can start building as soon as the land is registered.

So far, we've gone through the pre-colour and plan presentation stages. There has also been multiple meetings, phone calls with MJH, solicitor and mortgage broker with paper work that seems to go on for days.

Here are our timeline until today.

Date Event
Saturday, 2 May 2015 Deposit
Tuesday, 5 May 2015 Quotation received
Saturday, 9 May 2015 Deposit - no more structure change allowed
Wednesday, 13 May 2015 5% Deposit on land
Friday, 15 May 2015 Deposit Variation received - adding window to dining room at rear
Tuesday, 19 May 2015 Consolidated Tender received
Friday, 22 May 2015 Land contract received from solicitor
Monday, 1 June 2015 pre-colour selection -1hr
Tuesday, 2 June 2015 prelim plans received
Wednesday, 17 June 2015 Plan presentation - 40mins

Coming up: Colour selection on Wednesday, 8 July 2015!!

2 comments:

  1. Enjoying your blog. We are doing our colours selection this Friday with Mojo. Scary! Having said that your post was very encouraging about your appointment
    Thanks
    SArah

    ReplyDelete
  2. Thank you, Sarah!

    Hope you find our blog helpful and did well in your colour appointment!

    ReplyDelete