Saturday 13 February 2016

CONSTRUCTION - 08.02.2016 Roof DONE

Roof only took 2 days. This is how Austral Engage brick and Colourbond Windspray roof look like in the dark and in the sun.





CONSTRUCTION - 04.02.2016 Brickwork DONE

Brick is done. Only took 9 business days. It looks pretty straight from the sides. However, I did found the lines around the windows are not straight.

Need to organise an appointment to walk through and have a closer look at everything.

Roof started right away. When we visited the site on the weekend, sarking and fascia have been put on, half of the roof has been installed as well. Just waiting for eaves and the other half of the roof to be put on. Downpipes might be installed at the later stage.



Say 'hi' to my new neighbours :)