Friday 18 March 2016

CONSTRUCTION - 18.03.2016 Tiling Check DONE

We are now moved on to STEP 5: LININGS, KITCHENS & TILING in MJH's 8 steps. (MJH - 8 steps), next step is PRACTICAL COMPLETION!

We had the second last inspection with our Site Supervisor (SS) on Friday, 18th Mar 2016. Waterproofing, internal doors, kitchen cabinets and bathroom vanities are all completed.

Our SS check the tiles with us, as well as how the tiles are going to be laid. Tiling commenced on the same day, and painting will start after Easter break.


Internal doors - Danish style (upgrade)



 -  Ensuite shower

- Vanity - 3 drawers (upgrade)

- Main bathroom


- Bathroom tiles ( wall - white, floor - grey)

- Kitchen (fridge cabinets, pantry, wall cabinets (lip, no handle), pot drawers, etc.

- Kitchen island

CONSTRUCTION - 11.03.2016 LOCK UP

Electrical and pipes went in after roof was done, which was a quick job.

Then it took around 2 weeks to put on the walls (and filling the gaps between the plasterboards, etc.), cornices, skirtings (for carpet) and architrave.

During which time, garage door and external doors were installed and internal doors were delivered.

On 11th March, we received the message from MJH saying it's now officially locked up. =]

- Garage door (single) is called Heritage short panels, surfmist colour



CONSTRUCTION - 21.02.2016 Electrical DONE

During electrical walk through, our Site Supervisor check every single item on the list with us. All electrical items (light, power points, phone line, etc) were marked on the floor.

It was a very short walk through.