Building the Hamilton Three with McDonald Jones Homes
Monday 16 May 2016
CONSTRUCTION - 16.05.2016 PCI DONE
›
PCI!!!!! We cannot believe that 1 year after putting the deposit down on the H&L package, we are so close to the finish line! Alt...
CONSTRUCTION - 16.04.2016 One month later..
›
One month later.... Other than the 2-week delay on the floorings, everything else was moving fast. Driveway was ready to be poured ...
Friday 18 March 2016
CONSTRUCTION - 18.03.2016 Tiling Check DONE
›
We are now moved on to STEP 5: LININGS, KITCHENS & TILING in MJH's 8 steps. ( MJH - 8 steps ), next step is PRACTICAL COMPLETION! ...
CONSTRUCTION - 11.03.2016 LOCK UP
›
Electrical and pipes went in after roof was done, which was a quick job. Then it took around 2 weeks to put on the walls (and filling the ...
CONSTRUCTION - 21.02.2016 Electrical DONE
›
During electrical walk through, our Site Supervisor check every single item on the list with us. All electrical items (light, power points, ...
Saturday 13 February 2016
CONSTRUCTION - 08.02.2016 Roof DONE
›
Roof only took 2 days. This is how Austral Engage brick and Colourbond Windspray roof look like in the dark and in the sun.
CONSTRUCTION - 04.02.2016 Brickwork DONE
›
Brick is done. Only took 9 business days. It looks pretty straight from the sides. However, I did found the lines around the windows are ...
›